10 Sastry st art s working o n a jo b and wo rks on it for 12 day s and co mpletes 40% of the
work. To help him co mplet e the work, he employs R avi and t ogether they work for
another 12 day s and the work gets completed. How muc h more efficient is Sastry t han
Ravi?
(a) 50% (b) 200% (c) 60% (d) 100%
Read Solution (Total 5)
-
- S do 40% in 12 days
R+S do 60% in 12 Days
as S do 40% therefore R will do 20%
So S:R=2:1
therefore S is 100% efficient - 12 years agoHelpfull: Yes(9) No(1)
- 100%
Sastry can complete the work in 30 days
whereas Ravi can complete work in 60 days.
So Sastry is 2 times efficient as compared to Ravi
so Sastry is 100% more efficient than Ravi. - 12 years agoHelpfull: Yes(7) No(5)
- d)100%
Sastry's 12 days work=40%,So Sastry's 1 day work in %=40/12=10/3
Remaining work=60%, which is completed in another 12 days
If Ravi's 1 day work=1/R, then 12(10/3 + 1/R)=60 -> 1/R=5/3
The ratio Sastry/Ravi=(1/S)/(1/R)=(10/3)/(5/3)=2
This means Sastry is double or 100% more efficient than Ravi
- 12 years agoHelpfull: Yes(3) No(1)
- shastri takes 30 days
ravi takes 60 days
shastri/ravi=1/2
2*shastri=ravi.
if ravi efficiency is 100%, shastri efficiency is 200% - 12 years agoHelpfull: Yes(1) No(3)