x completes (1/3)rd of the work in 4 days, y completes (1/6)th of the work in 3days, z completes (1/2) of the work in 5 days. If x,y,z work for 3 days and then x,z left, how many days will y take to complete the remaining work?
Read Solution (Total 3)
-
- x complete work in 12days
y complete work in 18days
z complete work in 10days
together they work for 3 days ie 43/180 work complete
nw x,z left
therefore 43*3/180+x/18=1
hence x=51/10days - 12 years agoHelpfull: Yes(30) No(1)
- x's 1 day work=1/12
y's=1/18
z's=1/10
now work done by all(x+y+z) in one day =1/12+1/18+1/10=43/180
work done by all(x+y+z) in 3 days=3*43/180=43/60
remaining work=1-43/60=17/60
therefore no. of day required by y alone=18*17/60=5.1 days
- 12 years agoHelpfull: Yes(6) No(0)
- x's 1 day work=1/12
y's=1/18
z's=1/10
now x+y+z=43/180
remaining work 1-(43/180)
=137/180
time taken by y will be= (137/180)*18=aprrox 14 - 12 years agoHelpfull: Yes(2) No(6)
TCS Other Question
two rectangles with vertices A(0,0),(0,4),(-2,0),(-2,4) and B(1,0),(5,0),(1,12),(5,12) are bisected with a line, what is the slope of the line?
a)1
b)4
c)-1
d)-4
Eesha lies on mondays, tuesdays, wednesdays. Usha lies on thursday, friday, saturday.
Eesha said: i lied yesterday
Usha said: i lied yesterday
What is today?