7. x takes 4 days to complete one third of a job, y takes 3 days to complete one sixth of the
Same job and z takes 5 days to complete half of the job.If all of them work together for 3 days and x and z quit, how long will it take for y to complete the remaining work done?

Read Solution (Total 4)

TCS Other Question

2. Father is 5 times as efficient than the son and can do work in 40 days earlier.In how many days can they do work together? 8. Find the last two digits of (1941^3881)*(1961^4181)