A n B can do a work together in 5 days.if A double his speed and B half his speed then they can do it in 4 days.How many days taken if A alone do this work?
Read Solution (Total 4)
-
- 1/a+1/b=1/5
now,acc to the quest,a double his speed and b half his speed
therefore,it can be written as
2/a+1/2b=1/4
on solving these 2 eq,we get A=10 - 12 years agoHelpfull: Yes(55) No(0)
- (A=1)+(B=4)==5.... (2A)+ (1/2*B)==4 A alone == 25 days
- 12 years agoHelpfull: Yes(0) No(11)
- 1/a+1/b=1/5
now,acc to the quest,a double his speed and b half his speed
therefore,it can be written as
2/a+1/2b=1/4
on solving these 2 eq,we get A=10 - 12 years agoHelpfull: Yes(0) No(5)
- let one day work be a and b
a+b=1/5
2a+b/2=1/4
solving a=1/10
answ is 10 days - 12 years agoHelpfull: Yes(0) No(0)