15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers how many more days are needed to finish the remaining job ?
(a) 2 (b) 4 (c) 5 (d) 6
Read Solution (Total 6)
-
- 15 programar 3 days work=1
1 programar 1 day work=1/(3*15)=1/45
15 programar 1 day work=15/45=1/3
remainder work=2/3
9 programar 1 day work=9/45=1/5
so,
9 programar 1/5 work= 1day
9 programar 1 work=5day
2/3work=5*2/3
=3.3days=4days
hence ans is 4 days - 12 years agoHelpfull: Yes(11) No(13)
- sooorryyyy guyzz.....
The best answer is c.
The total working days for finishing a web page are (15 x 3) 45. If after one day 9
programmers quit, only 15 working days are done and the rest of the programmers (6)
Need to finish (45 – 15) 30 days of work. It will take them 5 more days. - 12 years agoHelpfull: Yes(11) No(5)
- The best answer is A.
The total working days for finishing a web page are (15 x 3) 45. If after one day 9
programmers quit, only 15 working days are done and the rest of the programmers (6)
Need to finish (45 – 15) 30 days of work. It will take them 5 more days. - 12 years agoHelpfull: Yes(6) No(5)
- frinds read question carefully it is a dummy bit.he did not specify 9 programmers dropped clearly.
- 10 years agoHelpfull: Yes(3) No(2)
- 15 workers complete in 3 days..
so man*day=constant
15*3=45 man.day
now 1 day and 15 workers so
1*15=15 man.day
so left man day 45-15=30 man.day
now 6 man left so,
6 man*day=30 man*day=5 days
now total days 5+1=6 days
ans=6 - 12 years agoHelpfull: Yes(1) No(10)
- (d)6 i used cross multiplication in 15->3then 9-x so x=6
- 8 years agoHelpfull: Yes(0) No(0)