Kamal can do a work in 15 days . Vimal is 50% more efficient than kamal . Then in how many days will Vimal do the work? 1) 13 days 2) 10 days 3) 10.5 days 4) none of these
Read Solution (Total 2)
-
- 2) 10 days
Kamal's 1 day work=1/15 Therefore Vimal's 1 day work=(1/15)*1.5=1/10
So Number of days Vimal takes to complete the work=1/(1/10)=10 - 11 years agoHelpfull: Yes(1) No(0)
- Kamla takes 15 days to complete 1 work so her 1 day work is 1/15.
Vimla is 50% more efficient than Kamla means= (1/15* 150/100) = 1/10, is Vimla's 1 day work. Answer
If both do it together then 1/10+ 1/15= 1/6. So together they would take 6 days. - 9 years agoHelpfull: Yes(0) No(1)