MBA Exam Numerical Ability Time and Work

Acc. to a plan a drilling team had to drill a depth of 270 mtrs. below the ground level. For the first 3 days the team drilled as per the plan. However subsequently finding that their resources were getting underutilized acc. to the plan, it started to drill 8 more mtrs. than the plan every day. therefore the day before the planned date they had drilled to a depth of 280 mtrs. how many mtrs of drilling was the plan for each day.

1) 38 metres
2) 30 metres
3) 27 metres
4) 28 metres

Read Solution (Total 1)