6 boys and 8 girls finish a job in 6 days and 14 boys and 10 girls finish the same job in 4 days. In how many days working together 1 boy and 1 girl can finish the work?
Read Solution (Total 1)
-
- 6B+8G=1/6 1
14B+10G=1/4 2
solve these equation to calculate the value of B and G
this give you the anser - 9 years agoHelpfull: Yes(0) No(0)