A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns rs.15/hr. How much does he earn from the whole job?
a)rs.90
b)rs.165
c)rs.105
d)rs.75
Read Solution (Total 6)
-
- c) Rs. 105
If A & B each works alternatively for 1 hr., then their 2 hr. work=(1/12)+(1/14)=13/84
So in 12 hr. 6 times of this work will be completed=6*13/84=39/42, Remaining work=1/14
Now again A's turn will be to complete next 1/12 work which will he requires 1 hr.
So A's total work=6+1=7 hr. and earning from the job @Rs. 15/hr= 7*15=105 - 9 years agoHelpfull: Yes(15) No(3)
- Assume total work is 84
A's 1 day work is 7
B's 1 day work is 6
so both can do (A+B)'s 1 day work is 13
13*6=78
and 6 is remaining from total wotk
for 6 days A earned 90
and for extra 6 work total A earned is 105 - 9 years agoHelpfull: Yes(6) No(3)
- (AB AB AB AB AB AB) A
(AB AB AB AB AB AB) UPTO THIS 13/14 th of work is done.
and next is A's turn whose capability is to do 1/12th of work in 1 hr so he does the remaining work which is 1/13th of work.
So A's turns are 7. so 7*15 =105 rupees
- 9 years agoHelpfull: Yes(5) No(3)
- I think its c because to complete the work they 12 6/7 days.(1/12+1/14=13/84)so they take 12 6/7 days.so a wrks for 6 6/7 days so 90+12=102
- 9 years agoHelpfull: Yes(3) No(9)
- ans =(90)
- 9 years agoHelpfull: Yes(2) No(11)
- ANSWER IS 90.
THEY DO IT ALTERNATIVELY EACH HOUR SO A TOTALLY DOES WORK FOR 6 HOURS AND IS PAID RS 15 PER HOUR SO, 15*6 = 90 IS THE ANSWER.
WE ARE NOT BOTHERED ABOUT THE 14 HOURS OF WORK DONE BY B AS TAKES ONLY 12 HOURS TO COMPLETE. THE EXTRA 2 HOURS WORK IS DONE BY B NOT BY A. - 6 years agoHelpfull: Yes(0) No(2)