A and B can complete a work in 12 days,while B and C can complete the same work in 20 days.When working together C leaves the work after 4 days.In how many days can A and B can finish the work.......
Read Solution (Total 3)
-
- what is the answer for the above unsolved question ?
- 8 years agoHelpfull: Yes(0) No(2)
- a+b=1/12
b+c=1/20 - 6 years agoHelpfull: Yes(0) No(2)
- here,
A+B=12
B+C=20
frist we find the One day work,
By taking LCM,
60
B+C=3
A+B=5
They working together:
A+B+B+C=8
A+B+C=4 .............(1)
now,
we know the value of A+B frist day put it in (1)
5+c=4 hence C=1
C work together for 4 days so 1X4=4 unit per day C works.
total unit work 60.
60 - 4=56
A+B=5
the remaining work 56 unit will finished by A+B in 56/5 days i.e 11.2 days - 6 years agoHelpfull: Yes(0) No(0)