30 workers can complete a job in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days:
A) 12
B) 10
C) 6
D) None of these
Read Solution (Total 2)
-
- C) 6
30 worker's 1 day work=1/20 and
21 worker's 1 day work=21/(30*20)=7/200
If 9 workers leaves after 'x' days, then 30 workers works for 'x' days, so 30-9=21 worker will work for 26-x days to complete the work.
So (x/20) + (26-x)*7/200= 1
x=6 - 9 years agoHelpfull: Yes(3) No(0)
- we can solve this ques also through options.
- 9 years agoHelpfull: Yes(0) No(0)