2 men and 1 women together can complete a piece of work in 14 days, while 4 women and 2 men together can do it in 8 days. if a man get rs 600 per day, how much should a women get per day?
Read Solution (Total 2)
-
- 400 Rs.
If 1 day work of a man & a woman is 'M' & 'W' respectively, then
2M + 1W= 1/14 ---(i) &
2M + 4W= 1/8 ---(ii)
On solving (i) & (ii), W=1/56, M=3/112
If for a work of 3/112 a man get Rs 600 per day, then for a work of 1/56, a woman will get
600*(1/56)/(3/112)=400 - 9 years agoHelpfull: Yes(3) No(0)
- 400/-.
12M=18W SO
M:W =3:2
IF M=600 W= 400 - 9 years agoHelpfull: Yes(0) No(3)