20 men can complete a piece of work in 16 days. after 5 days from the start of the work, some men left. if the remaining work was completed by the remaining men in 18 1/3 days, how many men left after 5 days from the start of the work?
Read Solution (Total 1)
-
- after 5 days of work , 8 men left.
in 5 day 5/16 work complete and 11/16 work remaning
1man-1day- 1/16*20 work
x men left and y work
(1/(16*20)) *y*55/3 =11/16
y=12 men
x=20-12=8 - 9 years agoHelpfull: Yes(3) No(0)