Numerical Ability
Time and Work
if A alone does the work in 15 days,how much time will A and B take working together to complete the job,given that A is 30% more efficient than B?
Read Solution (Total 15)
-
- ratio of times taken by A and B is=100:130
suppose B takes x days to do the work.
100:130::15:x
x=130*15/100=39/2.
B's 1 day's work=2/39
A's 1 day's work=1/15
(A+B)'s 1 day's work=69/585
A & B together can complete the work in 585/69 days.. - 8 years agoHelpfull: Yes(25) No(27)
- efficiency ratio of A:B=13:10
time ratio of A:B=10:13
so,10:13=15:x
so,x=39/2
so,time taken by A=15(given)
time taken by B=39/2(calculated)
efficiency 1/15:2/39=13:10 [taking LCM(15,23)=195 which is total work]
Now,(A+B) does 23 unit in 1 day
195 unit in 195/23 days(ans) - 8 years agoHelpfull: Yes(23) No(1)
- A's 1 day work=1/15
A is 30% more efficient than b
So B's 1 day work= 1/15-(30/100*1/15)
=7/150
S0 A+B 's 1 day work=1/15+7/150=17/150
so they will take 150/17 days .
- 8 years agoHelpfull: Yes(11) No(8)
- time taken by a and b = 100:130 :: 15:x
ad = bc
x=( 130*15)/100
x= 39/2
A's 1 day work = 1/15
B's 1 day work = 2/39
total = (1/15)+(2/39) = 23/ 195
ans is 195/23 - 8 years agoHelpfull: Yes(10) No(1)
- I think all the solutions provided are a mistake.
Let Time taken by B is x days.
since A is 30% more efficient than B
i.e.,if B takes 10 days then A sud take 7 days.
Then, x+(30/100)x=15
x=150/13.
(A+B) combined 1 day's work=(1/15 + 13/150)=23/150
Hence (A+B) can finish together in 150/23 days. - 8 years agoHelpfull: Yes(8) No(6)
- efficency ratio=130:100
since efficency inversely proportion to time
Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.
Then, 10 : 13 :: 15 : x => x = (15 x 13)/10 => x =39/2
A's 1 day's work = 1/15;
B's 1 day's work = 2/39 .
(A + B)'s 1 day's work=1/15+2/39=23/195
Therefore, A and B together can complete the work in 195/23 days. - 8 years agoHelpfull: Yes(5) No(2)
- let B=100;
A 30 % more than B so A=300;
A can do work in 15 days
B---------------?
100--------------?------B
130--------------15----A
100:130=?:15
B=150/13
A one day work 1/15
B one day work 150/13
A+B=1/15+13/150=23/150
- 8 years agoHelpfull: Yes(1) No(2)
- 585/65suppose B takes x days to do the work.
100:130::15:x
x=130*15/100=39/2.
B's 1 day's work=2/39
A's 1 day's work=1/15
(A+B)'s 1 day's work=69/585
A & B together can complete the work in 585/69 days. - 6 years agoHelpfull: Yes(1) No(0)
- efficiency ratio of A:B=13:10
time ratio of A:B=10:13
so,10:13=15:x
so,x=39/2
so,time taken by A=15(given)
time taken by B=39/2(calculated)
(A+B)'S 1 day work =(1/15 +2/39) =6/65
=> 1 complete work done by (A+B)= 65/6 days - 8 years agoHelpfull: Yes(0) No(4)
- ratio of times == 130:100
if b takes x days
130:100 :: 15 :x
13x=150
x =150/13
=> b takes 150/13 dayz
a +b = 1/15 + 13/150 = 23/150 =>15/23 days
- 8 years agoHelpfull: Yes(0) No(4)
- @shalini kumari u made a mistake in finding LCM of 39 and 15
- 8 years agoHelpfull: Yes(0) No(0)
- ans= 195/23 days
- 8 years agoHelpfull: Yes(0) No(0)
- 195/23 is right
- 8 years agoHelpfull: Yes(0) No(0)
- AS A IS 30% EFFICIENT THEN RATIO OF A: B IS:-
100:130 ~10:13
A ALONE DOES IN 15 DAYS THEN TOTAL WORK WILL BE:-
15*10=150 UNIT
HENCE A AND B TOGETHER WILL DO IN :-
150/10+23 =195/23 ~ 9 DAYS - 7 years agoHelpfull: Yes(0) No(0)
- A=15days
A+B=?
consider
B =100work in 1day
then A=130 in 1day
so,
A+B=230 in 1day
A=130*15 in 15days
A+B= 130*15/230= 9days - 7 years agoHelpfull: Yes(0) No(0)