A,Band C working together can complete a work in 8/3 hours. if A works at half of his speed and C works at twice his speed, the time taken to complete the work (all three still working together) remains same. if B decreases his speed by 50%, the time taken by B to complete the work becomes equal to time taken by C. Find the time taken (in hours) to complete the work if only A and C work together?