6 men can cut 12 trees in 8 days working 4 hours per day.in how many days can 12 men cut 48 trees working 8 hours a day
Read Solution (Total 1)
-
- 8 days
By 6 men in 8 days, working 4 hrs per day, let the work of cutting 12 trees= W, then
By 12 men in D days, working 8 hrs per days, the work of cutting 48 trees= 4W
=> (6 x 8 x 4)/W = (12 x D x 8)/4W
=> D =4*(6 x 8 x 4)/(12 x 8) = 8 - 7 years agoHelpfull: Yes(0) No(0)