MBA
Exam
If 20 men complete a work in 40 days. But onvery first day 1 person turns up, on 2nd day 2 , on 3rd day 3 and so on, how many days will it take to complete the work? 1) 39.5 2) >39.5 3) Work can never be completed
Read Solution (Total 1)
-
- 20 men complete a work in 40 days. so 800 man days
1+2+3+..n= 800
n=39.5 - 11 years agoHelpfull: Yes(0) No(0)
MBA Other Question