A is 20% more efficient than B. If B can complete a piece of work in 30 days, then in how many days can both A and B complete the work 1) 11*5/11 2) 13*7/11 3) 15*7/11 4) 17*5/11
Read Solution (Total 1)
-
- b takes 30 days
A will take 30*100/120=25 days
so both will take= 25*30/(25+30)
150/11
13_7/11 days is solution - 11 years agoHelpfull: Yes(0) No(0)