16 women take 12 days to complete a work which can be completed by 12 men in 8 days.16 men started working and after 3 days 10 men left and 4 women joined them.how many days will it take then to complete the remaining work?
Read Solution (Total 4)
-
- Ans: 6 days
- 7 years agoHelpfull: Yes(6) No(2)
- ans : 6 days
16 women take 12 days to complete a work.
in one day 16 women do 1/12 th of work.
in one day 1 woman does 1/(16*12) = 1/192 th of work.
12 men do same work in 8 days.
1 man can do in one day 1/96 th of work.
16 men for 3 days did = 16 * 1/96 * 3 = 1/2 of work.
now there are : 6 men and 4 women.
They can do in one day : 6 * 1/96 + 4 * 1/192 = 1/12th of work
Hence they take 6 days to complete the remaining 1/2 of work. - 6 years agoHelpfull: Yes(1) No(0)
- Ans: 31/5 days
- 7 years agoHelpfull: Yes(0) No(1)
- Ans : 5 1/2days
- 6 years agoHelpfull: Yes(0) No(1)