. A group of labourers are building a villa. After half the villa has been built, double the number of labourers joins the original group. The villa is completed 8 days earlier. What is the total number of days needed to complete the wall by the initial group of men?
Read Solution (Total 1)
-
- Let 'x' men complete the wall in 'y' days.
According to question, xy = 2x(y-8) [Equating rate of work]
=> y = 2y - 16
=> y = 16
so, in 16 days the wall is completed by initial group of men. - 7 years agoHelpfull: Yes(0) No(0)