MBA
Exam
P takes a days to complete a piece of work. Q takes d days more than P to complete the work. R takes d days more than Q to complete the work. S takes d days less than P to complete the work. T takes d days less than S to complete the work. Which of the following does not hold true? (d > 0) 1) R and S working together take more time to complete the work than Q and T do. 2) Q and S working together take more time to complete the work than R and T do. 3) Q and S working together take less time to complete the work than R and T do 4) R and T working together take less time then P and S do
Read Solution (Total 1)
-
- 3) Q and S working together take less time to complete the work than R and T do
is not true.
Time taken by Q and S = (a-d)*(a+d)/2a = (a^2-d^2)/2
Time taken by R and T = (a-2d)*(a+2d)/2a = (a^2-4d^2)/2
so Q and S working together will take 'more' time to complete the work than R and T do. - 11 years agoHelpfull: Yes(0) No(0)
MBA Other Question