GRE Exam Numerical Ability Time and Work

A and B can do a piece of work in 24 days, B and C can do it in 30 days and C and A can do it in 40 days. Which of the following statements is true? Indicate all correct options.
A. A takes 40 days to do the work
B. B takes 40 days to do the work
C. C takes 120 days to do the work
D. B takes 120 days to do the work
E. C takes 60 days to do the work

Read Solution (Total 1)