L&T Company Numerical Ability Time and Work

Some persons can do a piece of work in 36 days. Three times the number of these people will do one-fourth of that work in?

Read Solution (Total 1)

L&T Other Question

A, B and C can do a piece of work in 40, 30 and 24 days respectively. They start the work together but B leaves 6 days before the completion of the work. In how many days is the work completed? [A]14 [B]12 [C]13 [D]11 Two same glasses are respectively 2/5th 1/3th full of milk. They are then filled with water and the contents mixed in a tumbler. The ratio of milk and water in the tumbler is?