A certain number of men can finish a piece of work in 24 days. If however there were 10 men less it will take 8 days more for the work to be finished. How many men were there originally?
Read Solution (Total 1)
-
- (x-10)(24+8)=24x
(x-10)(32)=24x
x-10=(24/32)x
x-(24/32)x=10
32x-24x=10*32
8x=320
x=320/8
x=40
x= - 5 years agoHelpfull: Yes(1) No(0)