IBPS Government Jobs Exams Numerical Ability Time and Work

A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days, then C alone completed the remaining job in 22 days. In how many days C alone can complete the entire job? A) 45 B) 35 C) 40 D) 30 E) 48

Read Solution (Total 0)

IBPS Other Question

Among four consecutive odd numbers the sum of the squares of the first two numbers is 64 less than the sum of the squares of the next two numbers. Find the greatest of these four numbers. (A) 9 (B) 15 (C) 11 (D) 7 (E) 13 Rs. 7000 is divided unequally in two parts and invested in scheme A, which offers 10% p.a. compound interest which compounded annually and in scheme B, which offer 15% p.a. simple interest for 2 years and 3 years respectively. If the interest earned from scheme A is 84% of that earned from scheme B. Find the sum invested in scheme A. A) Rs. 4200 B) Rs. 2700 C) Rs. 3000 D) Rs. 4000 E) Rs. 4500