215:474::537::?

Read Solution (Total 1)

MBA Other Question

A, B, C can complete a work in 15 20 and 30 days respectively. they all work together for 2 days then A leaves the work. B and C work for somedays and B leaves 2 days before completion of the work. how many days are required to complete the whole work?