A can complete a piece of work alone in x days but B takes (2x–4) days to complete the same piece of work. If the efficiency of B is 40% less than that of A, then in how many days A and B together can complete the piece of work?
A) 6 days B) 8 days C) 7.5 days D) 12.5 days E) None of these