Sixteen men and twelve women can complete a work in 8 days. If 20 men can complete the same work in 16 days, in how many days 16 women can complete the same piece of work ?
A) 12 B) 8 C) 10 D) 15 E) 20

Read Solution (Total 0)

IBPS Other Question

Ronnie invested Rs.P in a scheme A offering simple interest at 12% p.a. for two years. He invested the whole amount he received from scheme A, in another scheme B offering simple interest 15% p.a. for two years. If the difference between the interest earned from schemes A and B was Rs. 264/, what is the value of P ?