Numerical Ability
Time and Work
2 employees and 3 trainees together can finish a project in 7 days, 6 employees and 13 trainees together can finish the same project in 2 days. Find the time taken by 4 employees and 4 trainees together to finish the same work.
A) 5 days B) 8 days C) 4 days D) 6 days E) 7 days