IBPS Government Jobs Exams Numerical Ability Time and Work

30 laborers working 7 hours a day can finish a piece of work in 18 days. If the laborers work 6 hours a day, then the number of laborers required to finish the same piece of work in 30 days will be
A) 15 B) 21 C) 25 D) 22 E) 28

Read Solution (Total 0)

IBPS Other Question

A trader marks his goods 30% above the cost price and gives a discount of 15% on the marked price. What percentage gain does he make?
A) 10.5% B) 15% C) 10% D) 14.5% E)
16.5%
If two men or six women or four boys can finish a work in 99 days, then how many days will one man, one woman and one boy together take to finish the same work?
A) 54 days B) 64 days C) 44 days D) 104 days E) 108 days