In how many days can the work be done by 9 men and 15 women?
I. 6 men and 5 women can complete the work in 6 days.
II. 3 men and 4 women can complete the work in 10 days.
III. 18 men and 15 women can complete the work in 2 days.
A) III only B) All I, II and III C) I and II D) Any two of the three E) Any one of the three