A, B, and C together can complete a piece of work in 25 days. A and C together can complete 30% of the work in 12 days and B and C together can complete 75% of the work in 33 days. A is 50% more efficient than C. In how many days (approximate integer value) B alone can complete the whole work?
A) 72 days B) 75 days C) 79 days D) 85 days E) 82 days