A constructor estimates that 4 people can paint Mr Khuranas house in 9 days. If he uses 6 people instead of 4, how long will they take to complete the job?
A)5 B)7 C)4 D)6
Read Solution (Total 2)
-
- Formula M1*D1 = M2*D2
9*4 = 6*x
=> x = 6 days - 4 years agoHelpfull: Yes(1) No(0)
- ans = 6 days
explanation = M1*D1 = M2*D2 = 4*9=6*D2 =6 DAYS - 4 years agoHelpfull: Yes(1) No(0)