A, B and C can do a piece of work in 30, 40 and 20 days respectively. They start the work together but C leaves 6 days before the completion of the work. In how many days is the work done?
A)10 days B)15 days C)18 days D)12 days
Read Solution (Total 1)
-
- A=30
B=40
C=20
LCM of 30,40,20 is 120
A=120/30
A=4
B=120/40
B=3
C=120/20
C=6
C leaves 6 days before the work gets completed that means for the 6 days only B and A where working
6=w/7
w=42
that is A and B worked 42 units of work after C left
the work done with C was
120-42
=78
that is in the initial days they carried out 78 units of work that is A,B,C
to calculate the days taken by them is
78/13 (where 4+3+6=13 this 4,3,6 are efficiency of A,B,C)
6 days taken by A,B,C
therefore A,B took 6 days and A,B,C also took 6 days
toghether they took=6+6=12 days - 4 years agoHelpfull: Yes(2) No(1)