Akash and Suraj can together finish a work in 18 days. They worked together for 12 days and then Suraj left. After another 10 days, Akash finished the remaining work. In how many days Akash alone can finish the work?
A)24 B)36 C)30 D)45
Read Solution (Total 4)
-
- I solved this without pen&paper.They worked together for 12 days remaining 6 days work can be completed by Akash in 10 days. If u consider akash is alone can complete the work..so,
6------>10
18---->?
=180/6=30 - 4 years agoHelpfull: Yes(8) No(0)
- A ans S together complete 1/18 work in one day
They work for 12 days so they complete 12/18=2/3 part of work
Remaining 1/3 part of work akash alone completed in 10 days so,
1/3 work= 10 days
1 work=30 days - 4 years agoHelpfull: Yes(2) No(0)
- A+S=1/18
(A+S)12+A(10)=1
(1/18)*12+A(10)=1
A(10)=1/3
A=30 - 4 years agoHelpfull: Yes(1) No(0)
- 30 days is the ans
- 4 years agoHelpfull: Yes(1) No(0)