4Q. Abhay, Pradeep & chandu can complete a work separately in 24, 36 & 48 days respectively. They started work together but Chandu left after 4 days of start and Abhay left 3 days before the completion of the work. In how many days will the work be completed?
a.) 22 Days
b.) 18 Days
c.) 15 Days
d.) 24 Days
Read Solution (Total 1)
-
- Let the work is completed in 'x' days.
Then, (x-3)/24 + X/36 + 4/48 = 1
Solving, we get X=15
So, option c) is correct. - 4 years agoHelpfull: Yes(1) No(0)