In the normal course, Rakesh, Sanket and Mukesh can each individually build a wall in 10,16 and 20 days respectively. Due to difficult terrain and slushy conditions at the site, the individual time required for each to complete the work has increased by 20%, 25% and 50% respectively. How long will they take to build the wall if they work together?
1)6 days 2)8 days 3)4 days 4)5½ days

Read Solution (Total 5)

TCS Other Question

Two finals are scheduled - The Wimbledon match and the World Cup Cricket at the same time. Anu wants to watch the Wimbledon finals and her brother Vinu wants to watch WCC final. They decide to roll a tetrahedral die twice. The tetrahedral is numbered 1,2,3,4 on its four sides and all numbers are equally likely to appear. Anu rolls first and then Vinu rolls. If the number on the first roll is strictly greater than the number on the second roll. Anu wins and gets to watch Wimbledon. What is the probability that Anu will get to watch Wimbledon?
1)7/16 2)9/16 3)3/8 4)1/2
A 3  3 grid is colored using red and blue
colors such that if we rotate the grid about
its center in the plane by 180 degrees, the
grid looks the same. The number of ways