A works thrice as much as B. If A takes 60 days less than B to do a work then find the number of days it would take to complete the work if both work together?
Read Solution (Total 4)
-
- if A finishes the job in x days
B finishes it in 3x days
3x = x + 60
thus
x = 30
in one hour
1/t = 1/30 + 1/90 = 4/90
where t is the number of days they finish the job together.
t = 90/4 = 22.5 days - 11 years agoHelpfull: Yes(14) No(2)
- Let A's rate be 3units/day and B's be 1unit/day.
Hence as A takes 60 days less than B to do a work,
Total units of work = 90units ( A takes 30days, B takes 90days)
=> If A and B work together, it will take 90/(3+1) days
=> 22.5 days - 13 years agoHelpfull: Yes(6) No(4)
- the ratio between a and b is 3:1
so 3x-x=60
and x = 30
so 1/90+1/30=221/2 days ans - 8 years agoHelpfull: Yes(3) No(3)
- ratio of work completed in days is 1:3.
Let A completed work in x days.
Then B will complete the wor in x+60 days.
=> x=30 days
1 day work of both A&b together is 1/30+1/60 =2/45.
They complete work in 45/2=22.5 days - 9 years agoHelpfull: Yes(0) No(0)