Ram, who is half as efficient as Krish, will take 24 days to complete a work if he worked alone. If Ram and Krish worked together, how many days will they take to complete the work?
A.
16
B.
12
C.
8
D.
18
Read Solution (Total 1)
-
- in 1 day they will together do (1/24+1/12) work
so total work will be done in 8 dys. - 10 years agoHelpfull: Yes(0) No(0)