A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time,each persons now working 9 hours a day.
Read Solution (Total 1)
-
- simple equation is 104*30*8*2/5 = X*26*9*3/5
=> X=160
=> so additional men required are 160-104=56 men - 6 years agoHelpfull: Yes(1) No(0)