SSC Government Jobs Exams Numerical Ability Time and Work

2 men and 5 women can do a work in 12 days. 5 men 2 women can do that work in 9 days. Only 3 women can finish the same work in-

Read Solution (Total 4)

SSC Other Question

250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is- While selling, a businessman allows 40% discount on the marked price and there is a loss of 30%. If it is sold at the marked price, profit per cent will be