A and B can finish a work in 12 days. B and C can finish the same work in 18days. C and A can finish in 24 days. How many days will take for A, B and Ccombined together to finish the same amount of work?

Read Solution (Total 0)

SSC Other Question

4 men or 8 women can do a piece of work in 24 days. In how many days, will12 men and 8 women do the same work A and B can do a piece of work in 12 days. B and C can do it in 20 days. If A is twice as good a workman as C, then in what time will B alone do it?