CMC
Company
HR Interview
Interview
Q. A and B can separately do apiece of work in 20 and 15 days respectively. They worked together for 6 days, after which B was replaced by C. If -the work was finished in next 4 days, then the number of days in which C alone could do the work will be
Option
a) 60
b) 40
c) 35
d) 30
Read Solution (Total 5)
-
- A and Bs one day work= 1/20+1/15=7/60
A and Bs six day work=(7/60)*6=7/10
remaining work=1-7/10=3/10
A and Cs 4 day work=(A and Cs 1 day work)*4= (1/20+1/x)*4=3/10 (remaining work)
x=40
Cs one day work=40 - 11 years agoHelpfull: Yes(21) No(0)
- (a+b)6days work=6(1/20+1/15)=7/10
(a+c)4days work=3/10
(a+c)1day work=3/40
a's 1day work=1/20
c's1day work=3/40-1/20=1/40
so answer is 40 - 10 years agoHelpfull: Yes(1) No(0)
- A's one day work is 1/20 days.
B's one day work is 1/15 days.
A and B is working together for 6 days,
total work of A and B for 6 days is,
(A's 1 day work x 6) + (B's 1 day work x 6)
(1/20 x 6) + (1/15 x 6)
(3/10) + (2/5)
(7/10)
remaining work is = 1- (7/10)
= 3/10
A's 4 days work is, (1/20) x 4=1/5
C's 4 days work is , 3/10 - 1/5 = 1/10
C's 1 day work is, (1/10) x (1/4)= 1/40
so that C can complete a work alone in 40 days. - 9 years agoHelpfull: Yes(1) No(0)
- b)
1 day work of a=(1/20)
1 day work of b= (1/15)
then days work =6*((1/20)+(1/15))=7/10
remaining work=(1-(7/10))=(3/10)
a n c complete (3/10)th work in 4 days
therefore
4*((1/20)+(1/x))=(3/10)
x=40
- 10 years agoHelpfull: Yes(0) No(0)
- Answer b) 40
A actually finish the work in 20 days....
But with B, A worked 6days and with C 4days totally 10days.
Means A worked for half of days.
I.e., 10days
So A completed 50% of work...
Then coming to B its worked for only 6days means its completed the work part of 6*1/15 =2/5
Total work completed is A's part + B's part = 1/2 +2/5 =9/10...
Only 1/10th part of work is pending and it is completed by C in 4 days..
1/10th part of work done in 4days
To finish the entire work...
10*4 = 40 - 8 years agoHelpfull: Yes(0) No(0)
CMC Other Question