Wipro Company Numerical Ability Time and Work

30 men take 20days to complete a job working 9 hours a day. how many hour a day should 40men work to complete the job?
a. 8hrs
b. 7 1/2 hrs
c. 7 rs
d. 9 hrs

Read Solution (Total 8)

Wipro Other Question

if radius of a circle is dimnished by 10% then its area is dimnished by
a) 10%
b) 19%
c) 20%
d) 36%
There are 3 red, 3 blue, 3 green marbles. What is probability that atleast two of them are of same color. If 3 marbles are done without replacement.