TCS
Company
Numerical Ability
Time and Work
55 men can finish a job in 42 days. if the work has to be completed 9 days earlier, how many additional men must be engaged to complete the work
Read Solution (Total 8)
-
- 55*42 proportional to 1 job.
x*(42-9) proportional to 1 job.
taking ratio .x=70.
hence extra men engaged = 70-55=15. - 11 years agoHelpfull: Yes(18) No(0)
- Use M1*d1*h1/w1= M2*d2*h2/w2 formula
Here we have oly men and days so apply to formula
The work has to be completed in 9days before that means work has completed in 33 days
55*42=(55+x)*33
x=15 - 11 years agoHelpfull: Yes(8) No(0)
- 55*42=x*33
=>x=(55*42)/33
=70
additional men require=70-55
=15 - 11 years agoHelpfull: Yes(4) No(0)
- 15 more men will be required
- 11 years agoHelpfull: Yes(0) No(0)
- please explain the solution
- 11 years agoHelpfull: Yes(0) No(0)
- 55*42=x*33
- 11 years agoHelpfull: Yes(0) No(3)
- 15 is correct
- 11 years agoHelpfull: Yes(0) No(0)
- no. of days is inversly propotional to no. of men .
and as no. of day decreased(42-9=33) so no. of men will increase, so the fraction would be 33/42.
now.... let total x men reqd to complete the work.
x/55=1/(33/42)
x=(42/33)*55=70
so additional men reqd=70-55=15