Numerical Ability
Time and Work
A is 6 times as fast as B and takes 100 days less to complete a work than B. find the total no of days taken by A and B to complete the work.
Read Solution (Total 8)
-
- Answer will be 120/7 days
Explanation:-
According to question A is 6 times as fast as B
So, Ratio of time taken by A and B will be 1:6
Let time taken by A is= x
and time taken by B is= 6x
According to the question A take 100 days less
i.e. 6x-x=100 ====>> x=20
So, A takes 20 days and B takes 120 days to complete the work..
A's 1 day work = 1/20
B's 1 day work = 1/120
(A+B)'s 1 day work = 1/20 + 1/120 = 7/120
total time taken = 120/7 days... Answer - 11 years agoHelpfull: Yes(30) No(2)
- A=20 days & B=120 days.. and together they will do the work in 17.14 days
- 11 years agoHelpfull: Yes(11) No(6)
- ratio of time taken by A n B is
a:b=1:6
b takes x days
then a takes x-100
so x-100/x=1/6
x=120
b takes 120 days n a takes 20 days
total 140 - 11 years agoHelpfull: Yes(9) No(17)
- 17 1/7 or 17.14 days
If A & B are the days taken to complete the work by A & B respectively
Given B-A=100 as A=B/6, so B-(B/6)=100 or B=120, A=20
Days to complete the work by A & B together=1/[(1/20)+(1/120)]=120/7=17 1/7 - 11 years agoHelpfull: Yes(7) No(3)
- A is 6 times faster than B.So,the time taken by B is B=6A
Given that A completes the work 100 days before B,then
B-A=100=>6A-A=100=>5A=100 and A=20,B=120
So,the total number of days taken by both is 140 days - 11 years agoHelpfull: Yes(3) No(4)
- A:B= 1:6
A-B= 100 Solving these eqns. u will get A=20 & B=120 total no.of days =140 - 11 years agoHelpfull: Yes(0) No(10)
- let total number of days taken by A be x,then B's total work will be done in 6x
then 6x-x=100--> x=20
therfore ans is 120 n 20 - 11 years agoHelpfull: Yes(0) No(2)
- Given n=6 and D=100,apply this rule D*n/n^2-1..
answer is 120/7
- 11 years agoHelpfull: Yes(0) No(1)