If 13 men can complete a piece of work in 36 days, then in how manydays will 18 men complete the same work?
Read Solution (Total 2)
-
- as work is same; we can write 13*36 = 18 *x ; x=26 days
- 9 years agoHelpfull: Yes(4) No(0)
- 13 men complete a piece of work in 36days
13M=1/36
M=1/468
18 men complete the same work in
18M=18/468
18M=1/26
18 Men completed the same work in the 26 days
Ans:26days - 11 years agoHelpfull: Yes(2) No(0)