Numerical Ability
Time and Work
Three persons undertake to complete a piece of work for Rs.1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?
Read Solution (Total 1)
-
- Money for first person = (1200/8)x3 = 450
Money for 2nd person = (1200/12)x3 = 300
Money for 3rd person = (1200/16)x3 = 225
Money for 4th person = 1200 – (450+300+225) = 225
- 10 years agoHelpfull: Yes(1) No(0)