SSC Government Jobs Exams Numerical Ability Time and Work

Three persons undertake to complete a piece of work for Rs.1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?

Read Solution (Total 1)

SSC Other Question

If x men can do a piece of work in x days, then the number of days in which y men can do the same work is? Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did, the work would have been completed in 3 days. To, complete the job alone, A would require how many days?