Numerical Ability
Time and Work
A and B working separately can do a piece of work in 9 and 12 days respectively. If the work for a day alternately with a beginning, the work would be completed in
Read Solution (Total 2)
-
- it takes 101/4 days to complete the work
- 11 years agoHelpfull: Yes(0) No(0)
- suppose the work needs x days to be done
(1/9*x/2)+(1/12*x/2)=1
x=72/7 days - 9 years agoHelpfull: Yes(0) No(0)