P is 30% more efficient than Q. P can complete a work in 23 days. If P and Q work together, how much time will it take to complete the same work?

Options
1) 9
2) 11
3) 13
4) 15

Read Solution (Total 1)

SSC Other Question

10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?

Options
1) 5
2) 6
3) 7
4) 8